CouncilTrac · Matter
Increase contract with Southern Trenchless for sewer manhole rehabilitation by $60,432.85
What this is
The city will increase Contract #324000342 with Southern Trenchless by $60,432.85 to cover additional work rehabilitating sewer manholes along Prairie Creek.
Council action
Motion to approve the Consent Agenda as presented
Moved by Ken Hutchenrider. Seconded by Curtis Dorian.
7 yes · 0 no
The approved minutes report the tally without a name-by-name roll call.
Timeline
- July 9, 2026 Agenda posted — August 25, 2025 meeting
- August 25, 2025 Vote taken — August 25, 2025 meeting · Approved 7-0 (consent)
Appearances on agendas
-
City Council — August 25, 2025
Approve contract increase
Official agenda language
TO INCREASE CONTRACT # 324000342 TO SOUTHERN TRENCHLESS FOR PRAIRIE CREEK SEWER MANHOLE REHABILITATION IN THE AMOUNT OF $60,432.85.
Documents
Related matters
-
Cooperative contract for Spring Creek sewer manhole rehab at $850,000 (Bid #61-26)
The city would hire Southern Trenchless Solutions to rehabilitate sanitary sewer manholes along Spring Creek through the BuyBoard cooperative (Contract #731-24) for up to $850,000.
-
Change order increasing waterline replacement contract by $74,536.75
The council would approve adding $74,536.75 to the existing contract with A&M Construction and Utilities, Inc. (Contract #326000038) for waterline replacement work at Coit at Promenade, Stillmeadow Drive, and Dunbarton Drive.
-
Approve $117,175 change order for sanitary sewer repairs over Beck Branch
Council will consider authorizing a change order increasing Contract #325000239 with Stoic Civil Construction, Inc. by $117,175 to cover sanitary sewer repairs over Beck Branch.
-
Award bid for Renner Road at Wyndham Lane large valve improvement ($275,445)
Council is asked to award Bid #01-26 to Pennington Concrete & Utilities, LLC for a water valve improvement project at the intersection of Renner Road and Wyndham Lane in the amount of $275,445.
-
Award $9.5 million contract for West Shore Drive and Fontana Avenue reconstruction
Council is asked to award Bid #83-25 to Estrada Concrete Company LLC for street and utility reconstruction on West Shore Drive and Fontana Avenue in the amount of $9,473,392.