CouncilTrac · Matter
Award $9.5 million contract for West Shore Drive and Fontana Avenue reconstruction
What this is
Council is asked to award Bid #83-25 to Estrada Concrete Company LLC for street and utility reconstruction on West Shore Drive and Fontana Avenue in the amount of $9,473,392.
Why it matters
This is a large combined street and utility project that will affect traffic patterns and utility service along West Shore Drive and Fontana Avenue.
Council action
Motion to approve the Consent Agenda as presented
Moved by Ken Hutchenrider. Seconded by Jennifer Justice.
7 yes · 0 no
The approved minutes report the tally without a name-by-name roll call.
Timeline
- July 9, 2026 Agenda posted — October 20, 2025 meeting
- October 20, 2025 Vote taken — October 20, 2025 meeting · Approved 7-0 (consent)
Appearances on agendas
-
City Council — October 20, 2025
Award bid
Official agenda language
BID #83-25 – WE RECOMMEND THE AWARD TO ESTRADA CONCRETE COMPANY LLC FOR WEST SHORE DRIVE AND FONTANA AVENUE STREET AND UTILITY RECONSTRUCTION IN THE AMOUNT OF $9,473,392.
Documents
Related matters
-
Award $3,649,318.85 contract for Canyon Brook, Canyon Valley, and Forest Grove street and utility improvements
Staff recommends awarding Bid #48-24 to KIK Underground, LLC in the amount of $3,649,318.85 for pavement and utility improvements in the Canyon Brook, Canyon Valley, and Forest Grove neighborhoods.
-
Award $686,924 contract for Wake Drive and Baylor Drive alley and sewer improvements (Bid #22-24)
The council is asked to award a contract to Candor Builder, LLC in the amount of $686,924 for paving and sanitary sewer improvements to alleys on Wake Drive and Baylor Drive as part of the 2021 Bond Alley Group 4 project.
-
Award $668,074 contract for alley and utility reconstruction on Fontana Ave. and West Shore Dr.
The city recommends awarding a contract to KIK Underground for $668,074 to reconstruct the north alleys and utilities in the 800 block of Fontana Avenue and to reconstruct the north alley in the 500 block of West Shore Drive.
-
Cooperative contract for Spring Creek sewer manhole rehab at $850,000 (Bid #61-26)
The city would hire Southern Trenchless Solutions to rehabilitate sanitary sewer manholes along Spring Creek through the BuyBoard cooperative (Contract #731-24) for up to $850,000.
-
Award Bid #27-26 for Campbell Road and University Drive intersection improvements
Staff recommends awarding Bid #27-26 to JR West Texas Concrete, LLC to make intersection improvements at Campbell Road and University Drive for $1,182,134.