CouncilTrac · Matter
Award $880,000 contract for Cottonwood Creek sanitary sewer manhole rehabilitation
What this is
Staff recommends awarding Bid #66-23 to Southern Trenchless Solutions in the amount of $880,000 for Phase 2 of the Cottonwood Creek Basin Sanitary Sewer Manhole Rehabilitation project, using BuyBoard cooperative contract #635-21.
Why it matters
Rehabilitating aging sewer manholes helps prevent sewage overflows and protects water quality for residents.
Council action
Motion to approve the Consent Agenda as presented
Moved by Ken Hutchenrider.
7 yes · 0 no
The approved minutes report the tally without a name-by-name roll call.
Timeline
- July 10, 2026 Agenda posted — April 10, 2023 meeting
- April 10, 2023 Vote taken — April 10, 2023 meeting · Approved 7-0 (consent)
Appearances on agendas
-
City Council — April 10, 2023
Award contract on consent
Official agenda language
BID #66-23 – WE RECOMMEND THE AWARD TO SOUTHERN TRENCHLESS SOLUTIONS FOR THE PURCHASE OF COTTONWOOD CREEK BASIN SANITARY SEWER MANHOLE REHABILITATION PHASE 2 PURSUANT TO THE LOCAL GOVERNMENT PURCHASING COOPERATIVE (“BUYBOARD”) CONTRACT #635-21 IN THE AMOUNT OF $880,000.
Documents
Related matters
-
Cooperative contract for Spring Creek sewer manhole rehab at $850,000 (Bid #61-26)
The city would hire Southern Trenchless Solutions to rehabilitate sanitary sewer manholes along Spring Creek through the BuyBoard cooperative (Contract #731-24) for up to $850,000.
-
Award bid for Renner Road at Wyndham Lane large valve improvement ($275,445)
Council is asked to award Bid #01-26 to Pennington Concrete & Utilities, LLC for a water valve improvement project at the intersection of Renner Road and Wyndham Lane in the amount of $275,445.
-
Award $9.5 million contract for West Shore Drive and Fontana Avenue reconstruction
Council is asked to award Bid #83-25 to Estrada Concrete Company LLC for street and utility reconstruction on West Shore Drive and Fontana Avenue in the amount of $9,473,392.
-
Award $420,723 contract for Collins Water Tower valve improvements (Bid #02-25)
The council will consider authorizing a contract with Ruts Construction, the lowest responsible bidder, for valve improvements at the Collins Water Tower in the amount of $420,723.
-
Award $1,121,464 contract for waterline replacement at Coit Road, Stillmeadow Drive, and Dunbarton Drive
Council will award Bid #62-25 to A & M Construction and Utilities, Inc. to replace water lines at Coit Road at Promenade Center, Stillmeadow Drive, and Dunbarton Drive for $1,121,464.