CouncilTrac · Matter
Authorize $20.77 million construction contract to expand city water pressure zone capacity
What this is
The council is asked to authorize the City Manager to execute a Guaranteed Maximum Price (GMP) Amendment No. 1 with Archer Western Construction, LLC for construction of water system improvements to expand the capacity of the city's 825 pressure zone, in the amount of $20,772,272.
Why it matters
This $20.77 million water infrastructure investment is aimed at improving the city's water distribution capacity, which affects reliability and service for Richardson water customers.
Timeline
- July 10, 2026 Agenda posted — November 14, 2022 meeting
Appearances on agendas
-
City Council — November 14, 2022
Authorize GMP amendment
Official agenda language
AUTHORIZE THE CITY MANAGER TO EXECUTE GUARANTEED MAXIMUM PRICE (“GMP”) AMENDMENT NO. 1 TO THE CONSTRUCTION MANAGER AT RISK (“CMAR”) AGREEMENT WITH ARCHER WESTERN CONSTRUCTION, LLC FOR THE CONSTRUCTION OF WATER IMPROVEMENTS TO EXPAND THE 825 PRESSURE ZONE CAPACITY OF THE CITY’S WATER DISTRIBUTION SYSTEM IN THE AMOUNT OF $20,772,272.
Documents
Related matters
-
Cooperative contract for Spring Creek sewer manhole rehab at $850,000 (Bid #61-26)
The city would hire Southern Trenchless Solutions to rehabilitate sanitary sewer manholes along Spring Creek through the BuyBoard cooperative (Contract #731-24) for up to $850,000.
-
Change order increasing waterline replacement contract by $74,536.75
The council would approve adding $74,536.75 to the existing contract with A&M Construction and Utilities, Inc. (Contract #326000038) for waterline replacement work at Coit at Promenade, Stillmeadow Drive, and Dunbarton Drive.
-
Approve $117,175 change order for sanitary sewer repairs over Beck Branch
Council will consider authorizing a change order increasing Contract #325000239 with Stoic Civil Construction, Inc. by $117,175 to cover sanitary sewer repairs over Beck Branch.
-
Award bid for Renner Road at Wyndham Lane large valve improvement ($275,445)
Council is asked to award Bid #01-26 to Pennington Concrete & Utilities, LLC for a water valve improvement project at the intersection of Renner Road and Wyndham Lane in the amount of $275,445.
-
Award $9.5 million contract for West Shore Drive and Fontana Avenue reconstruction
Council is asked to award Bid #83-25 to Estrada Concrete Company LLC for street and utility reconstruction on West Shore Drive and Fontana Avenue in the amount of $9,473,392.