CouncilTrac · Matter
Award $1.75 million contract to repair alleys in five neighborhoods
What this is
Council will award Bid #04-24 to Muniz Construction, Inc. for the 2021 Bond Alley Group 2 Project, covering Chestnut Hill Ln., Aurora Dr., Elk Grove Dr., Georgetown Dr., and Windsong Trail, for $1,751,295.
Why it matters
This bond-funded project will repair alleys serving residents in five neighborhoods.
Council action
Motion to approve the Consent Agenda as presented
Moved by Arefin Shamsul. Seconded by Ken Hutchenrider.
7 yes · 0 no
The approved minutes report the tally without a name-by-name roll call.
Timeline
- July 10, 2026 Agenda posted — May 6, 2024 meeting
- May 6, 2024 Vote taken — May 6, 2024 meeting · Approved 7-0 (consent)
Appearances on agendas
-
City Council — May 6, 2024
Award contract to Muniz Construction, Inc.
Official agenda language
BID #04-24 – WE RECOMMEND THE AWARD TO MUNIZ CONSTRUCTION, INC. FOR 2021 BOND ALLEY GROUP 2 PROJECT (CHESTNUT HILL LN., AURORA DR., ELK GROVE DR., GEORGETOWN DR., WINDSONG TRAIL) IN THE AMOUNT OF $1,751,295.
Documents
Related matters
-
Award Bid #27-26 for Campbell Road and University Drive intersection improvements
Staff recommends awarding Bid #27-26 to JR West Texas Concrete, LLC to make intersection improvements at Campbell Road and University Drive for $1,182,134.
-
Contract award for alley rehabilitation — Bid #08-26
Staff requests authorization to award an annual requirements contract to R&A Legacy Construction, LLC for alley rehabilitation work in the estimated amount of $1,170,871.27.
-
Contract award for neighborhood street rehabilitation — Bid #09-26
Staff requests authorization to award an annual requirements contract to R&A Legacy Construction, LLC for neighborhood street rehabilitation in the estimated amount of $2,157,170.
-
Award $2.5 million concrete contract for Richland Park street segments
Council is asked to award Bid #67-25 to Estrada Concrete Company for concrete work on two Richland Park street segments — Sheffield to Tiffany and Stillmeadow to Wentworth — for $2,546,841.
-
Award $9.5 million contract for West Shore Drive and Fontana Avenue reconstruction
Council is asked to award Bid #83-25 to Estrada Concrete Company LLC for street and utility reconstruction on West Shore Drive and Fontana Avenue in the amount of $9,473,392.