CouncilTrac · Matter
Award $3,184,555 contract for Main Street Phase II reconstruction from Greenville Avenue to Abrams Road
What this is
Bid #06-25 would award a construction contract to Urban InfraConstruction, LLC for $3,184,555 to complete Phase II of the Main Street project, running from Greenville Avenue to Abrams Road.
Why it matters
This street reconstruction project will affect traffic patterns and access along that segment of Main Street while work is underway, and will improve the roadway when complete.
Council action
Motion to approve the Consent Agenda as presented
Moved by Ken Hutchenrider. Seconded by Curtis Dorian.
7 yes · 0 no
The approved minutes report the tally without a name-by-name roll call.
Timeline
- July 10, 2026 Agenda posted — November 11, 2024 meeting
- November 11, 2024 Vote taken — November 11, 2024 meeting · Approved 7-0 (consent)
Appearances on agendas
-
City Council — November 11, 2024
Award construction contract
Official agenda language
BID #06-25 – WE RECOMMEND THE AWARD TO URBAN INFRACONSTRUCTION, LLC FOR CONSTRUCTION OF THE MAIN STREET PHASE II - GREENVILLE AVENUE TO ABRAMS ROAD PROJECT IN THE AMOUNT OF $3,184,555.
Documents
Related matters
-
Award Bid #27-26 for Campbell Road and University Drive intersection improvements
Staff recommends awarding Bid #27-26 to JR West Texas Concrete, LLC to make intersection improvements at Campbell Road and University Drive for $1,182,134.
-
Contract award for alley rehabilitation — Bid #08-26
Staff requests authorization to award an annual requirements contract to R&A Legacy Construction, LLC for alley rehabilitation work in the estimated amount of $1,170,871.27.
-
Contract award for neighborhood street rehabilitation — Bid #09-26
Staff requests authorization to award an annual requirements contract to R&A Legacy Construction, LLC for neighborhood street rehabilitation in the estimated amount of $2,157,170.
-
Award $2.5 million concrete contract for Richland Park street segments
Council is asked to award Bid #67-25 to Estrada Concrete Company for concrete work on two Richland Park street segments — Sheffield to Tiffany and Stillmeadow to Wentworth — for $2,546,841.
-
Award $9.5 million contract for West Shore Drive and Fontana Avenue reconstruction
Council is asked to award Bid #83-25 to Estrada Concrete Company LLC for street and utility reconstruction on West Shore Drive and Fontana Avenue in the amount of $9,473,392.