Discuss library renovation design and construction manager at risk selection
What this is
Council will review the design approach for the library renovation project and discuss the process for selecting a Construction Manager at Risk (CMAR) firm.
Why it matters
The library renovation is a significant public investment, and this discussion shapes how the project will be designed and managed.
Timeline
- July 10, 2026 Agenda posted — June 12, 2023 meeting
Appearances on agendas
-
City Council — June 12, 2023
Review and discuss — no formal vote at this stage
Official agenda language
REVIEW AND DISCUSS THE LIBRARY RENOVATION DESIGN AND CONSTRUCTION MANAGER AT RISK SELECTION
Documents
Related matters
-
Award $28,000 contract to Balfour Beatty for library renovation construction management
RFQ #2023-02 recommends awarding a Construction Manager at Risk (CMAR) services contract to Balfour Beatty Construction, LLC for the library renovation project in the amount of $28,000.
-
Discussion: Richardson Public Library renovation project update
Council will receive a briefing on the status of the ongoing Richardson Public Library renovation project and discuss any updates.
-
Approve change order increasing library renovation contract by $1,176,794
Council is asked to approve a change order that increases the existing library renovation contract with Balfour Beatty Construction LLC (Contract #324000263) by $1,176,794.
-
Update on the Richardson Public Library renovation project
Staff will present the current status of the library renovation project for council review and discussion.
-
Approve $1,176,794 change order to library renovation contract with Balfour Beatty
Staff requests authorization for a change order increasing Contract #324000263 with Balfour Beatty Construction LLC for the library renovation project by $1,176,794.