Award $28,000 contract to Balfour Beatty for library renovation construction management
What this is
RFQ #2023-02 recommends awarding a Construction Manager at Risk (CMAR) services contract to Balfour Beatty Construction, LLC for the library renovation project in the amount of $28,000.
Why it matters
This contract engages the firm that will oversee construction of the library renovation, affecting cost control and project delivery.
Council action
Motion to approve the Consent Agenda as presented
Moved by Ken Hutchenrider. Seconded by Jennifer Justice.
7 yes · 0 no
The approved minutes report the tally without a name-by-name roll call.
Timeline
- July 10, 2026 Agenda posted — June 12, 2023 meeting
- June 12, 2023 Vote taken — June 12, 2023 meeting · Approved 7-0 (consent)
Appearances on agendas
-
City Council — June 12, 2023
Award CMAR contract to Balfour Beatty Construction, LLC
Official agenda language
CONSIDER AWARD OF REQUEST FOR QUALIFICATIONS (“RFQ”) #2023-02 – WE RECOMMEND THE AWARD TO BALFOUR BEATTY CONSTRUCTION, LLC. FOR CONSTRUCTION MANAGER AT RISK ("CMAR") SERVICES FOR THE LIBRARY RENOVATION PROJECT IN THE AMOUNT OF $28,000.
Documents
Related matters
-
Discuss library renovation design and construction manager at risk selection
Council will review the design approach for the library renovation project and discuss the process for selecting a Construction Manager at Risk (CMAR) firm.
-
Discussion: Richardson Public Library renovation project update
Council will receive a briefing on the status of the ongoing Richardson Public Library renovation project and discuss any updates.
-
Approve change order increasing library renovation contract by $1,176,794
Council is asked to approve a change order that increases the existing library renovation contract with Balfour Beatty Construction LLC (Contract #324000263) by $1,176,794.
-
Update on the Richardson Public Library renovation project
Staff will present the current status of the library renovation project for council review and discussion.
-
Approve $1,176,794 change order to library renovation contract with Balfour Beatty
Staff requests authorization for a change order increasing Contract #324000263 with Balfour Beatty Construction LLC for the library renovation project by $1,176,794.